Financial Institution Data Center #1
Confidential Client

Capacity Expansion.

Recently upgraded through Data Center Expansion from 40W/SF to 80W/SF.
Upgrade included installation of equipment and commissioning in a live data center without impact to the data center loads. Project included the addition of:

  • Medium voltage unit substations
  • Three 2.0MW generators
  • Two 2,700kW multi-module UPS systems